Grid infrastructure › Connection queue › Battery storage
BATTERY STORAGE · SPTSand Quarry Old Glasgow Road BESS
Sand Quarry Old Glasgow Road BESS is a 100 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Giffordland 400/132kV, with capacity due from May 2029. The connection agreement is held by GPC 1134 Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom May 2029 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002706
- Customer
- GPC 1134 Ltd
- Technology
- Demand, Energy Storage System
- Total capacity
- 100 MW
- Change in this agreement
- +100 MW
- Capacity effective from
- 7 May 2029
- Connection site
- Giffordland 400/132kV
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Other projects at Giffordland 400/132kV
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem