🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

Stretchford Farm Solar and Storage

Stretchford Farm Solar and Storage is a 100 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Abham 132kV Substation, with capacity due from October 2037. The connection agreement is held by Bsr Applications Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004522
Customer
Bsr Applications Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
100 MW
Change in this agreement
+100 MW
Capacity effective from
30 October 2037
Connection site
Abham 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Abham · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem