United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2021 requests) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown896227.7 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

896 requests · page 7 of 18
ProjectCapacityStatusLocationRegionQueuedOnline
Geothermal project Company LM, Lyon County
Geothermal
230 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar project J2317, Ouachita Parish County
Solar
225 MWIn study Ouachita Parish, LAMISO Dec 2021target 2027
Solar project GEN-2021-049, Lancaster County
Solar
225 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Battery storage project 292, Pinellas County
Battery storage · Duke Energy Florida, LLC
225 MWUnder construction Pinellas, FLSoutheast Apr 2021target 2025
Allium Hybrid
Solar + storage
225 MWAgreement signed San Benito, CACAISO Apr 2021target 2030
Utley Solar
Solar
222 MWPaused / redesign Freestone, TXERCOT Sep 2021target 2025
Goodalta Solar
Solar · GoodAlta Power Center LLC
221 MWIn study Navarro, TXERCOT Jan 2021target 2027
Battery storage project Q83, Millard County
Battery storage · Intermountain Power Agency
220 MWIn study Millard, UTWest Sep 2021target 2024
Solar project J2001, Newaygo County
Solar
220 MWIn study Newaygo, MIMISO Aug 2021target 2025
Gas project 113, Lewis County
Gas
219 MWPaused / redesign Lewis, WAWest Jul 2021target 2029
Gas project 114, Kitsap County
Gas
215 MWPaused / redesign Kitsap, WAWest Jul 2021target 2029
Dorian Storage
Battery storage
214 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Zeus BESS
Battery storage
214 MWAgreement signed San Joaquin, CACAISO Apr 2021target 2031
Weston Storage
Battery storage
214 MWIn study San Bernardino, CACAISO Apr 2021target 2031
Frigatebird Storage
Battery storage
214 MWIn study San Diego, CACAISO Apr 2021target 2035
Grimes County Solar
Solar · Grimes County Solar Project, LLC
211 MWAgreement signed Grimes, TXERCOT Jan 2021target 2025
Val Vista Grid BESS 2
Battery storage · Val Vista Grid, LLC
211 MWIn study Hidalgo, TXERCOT Oct 2021target 2028
Two Rivers Solar
Solar · Two Rivers Solar, LLC
209 MWIn study Milam, TXERCOT Jul 2021target 2029
Alwest BESS
Battery storage · Castleman Power
209 MWIn study Anderson, TXERCOT Aug 2021target 2028
Bypass Battery Storage
Battery storage · Bypass BESS LLC
208 MWAgreement signed Fort Bend, TXERCOT Aug 2021target 2025
Umbra (Stockyard) Solar
Solar
208 MWPaused / redesign Franklin, TXERCOT Jan 2021target 2026
Erath County Solar
Solar · Erath County Solar, LLC
207 MWAgreement signed Erath, TXERCOT Mar 2021target 2029
Liberty Senate Energy Storage 1
Battery storage · Senate Solar LLC
207 MWIn study Jack, TXERCOT Oct 2021target 2027
Alamosa Storage
Battery storage
207 MWPaused / redesign Wilbarger, TXERCOT Oct 2021
BRP Hemera BESS
Battery storage · BRP Hemera BESS LLC
207 MWIn study Deaf Smith, TXERCOT Dec 2021target 2029
Hoyte Solar
Solar · Milano Solar LLC
207 MWAgreement signed Milam, TXERCOT Apr 2021target 2027
Desert Jewel Storage
Battery storage
206 MWAgreement signed San Diego, CACAISO Apr 2021target 2029
Sultan Solar
Solar
206 MWPaused / redesign Bosque, TXERCOT Jun 2021target 2026
Crios BESS
Battery storage · BRP Crios BESS LLC
206 MWIn study Comanche, TXERCOT Oct 2021target 2028
Trivor BESS
Battery storage · BRP Trivor BESS LLC
206 MWIn study Andrews, TXERCOT Jun 2021target 2028
Desna BESS
Battery storage · BRP Desna BESS LLC
206 MWAgreement signed Brazoria, TXERCOT Dec 2021target 2026
Ferdinand Grid BESS
Battery storage · Ferdinand Grid, LLC
206 MWAgreement signed Bexar, TXERCOT Mar 2021target 2026
Pajarita BESS
Battery storage · VESI 29 LLC
206 MWAgreement signed Cameron, TXERCOT Jan 2021target 2028
BRP Triton BESS
Battery storage · BRP Triton BESS LLC
205 MWIn study Comanche, TXERCOT Oct 2021target 2026
Castor BESS
Battery storage · BRP Castor BESS LLC
205 MWAgreement signed Brazoria, TXERCOT Oct 2021target 2026
Naugatuck Avenue Battery Storage
Battery storage
205 MWAgreement signed New Haven, CTISO-NE Jan 2021target 2027
Battery Storage
Battery storage
205 MWAgreement signed Washington, RIISO-NE Sep 2021target 2029
Limewood Solar
Solar + storage · Limewood Bell Renewables LLC
205 MWAgreement signed Bell, TXERCOT Apr 2021target 2026
Utica Solar
Solar
205 MWPaused / redesign Guadalupe, TXERCOT Apr 2021
Cornwall Solar
Solar
205 MWPaused / redesign Williamson, TXERCOT Feb 2021
Sahara BESS (Soho BESS)
Battery storage · ESTX-PLD-HOUSTON2
204 MWAgreement signed Brazoria, TXERCOT Dec 2021target 2026
Keys Hollow Solar Phase II SLF
Solar + storage · Keys Hollow Solar, LLC
204 MWAgreement signed Goliad, TXERCOT Jun 2021target 2028
Solar project GEN-2021-033, Franklin County
Solar
204 MWAgreement signed Franklin, ARSPP May 2021target 2028
Solar project GEN-2021-036, Little River County
Solar
204 MWAgreement signed Little River, ARSPP May 2021target 2027
Keys Hollow Solar SLF
Solar + storage · Keys Hollow Solar, LLC
204 MWAgreement signed Goliad, TXERCOT Jun 2021target 2028
Norman Street Battery Storage
Battery storage
204 MWAgreement signed Middlesex, MAISO-NE Mar 2021target 2028
Phaenon
Solar + storage
204 MWIn study Kern, CACAISO Apr 2021target 2029
Sowers Storage
Battery storage · Sowers Energy Storage LLC
204 MWAgreement signed Kaufman, TXERCOT Aug 2021target 2026
Huaso Hybrid
Solar + storage
204 MWAgreement signed Fresno, CACAISO Apr 2021target 2026
Puma Storage
Battery storage
204 MWIn study Madera, CACAISO Apr 2021target 2030
Page 7 of 18

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)