🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Desert Jewel Storage

Desert Jewel Storage is a 206 MW battery storage request with a signed interconnection agreement in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusConsented
  1. PlanningQueued Apr 2021 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
2173
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Boulevard East Substation 138 kV
Location
San Diego County, California
Technology
Battery: 206 MW
Total requested
206 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2021
Agreement signed
15 May 2025
Proposed online date
February 2029

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem