Tule Wind

Tule Wind is a 259 MW wind + storage request with a signed interconnection agreement in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusConsented
  1. PlanningQueued May 2004 (completed)
  2. ConsentedMar 2011 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
32
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Boulevard East Substation 138 kV
Location
San Diego County, California
Technology
Wind: 128 MW · Battery: 132 MW
Total requested
259 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
24 May 2004
Agreement signed
23 March 2011
Proposed online date
October 2030

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem