Erath County Solar is a 207 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Erath County, Texas.
Queue statusConsented
- PlanningQueued Mar 2021 (completed)
- ConsentedJun 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0202
- Grid region
- ERCOT (Texas)
- Developer
- Erath County Solar, LLC
- Connection point (POI)
- tap 345kV 68020 Romney1E - 68030 KopperlW
- Location
- Erath County, Texas
- Technology
- Solar: 207 MW
- Total requested
- 207 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 8 March 2021
- Agreement signed
- 1 June 2023
- Proposed online date
- January 2029
Location
Marker shows the centre of Erath County; the queue data does not give exact sites.
Other requests in Erath County
- McCrae Energy StorageBattery storage · 306 MW · agreement signed
- Glory Bee SolarSolar + storage · 305 MW · in study
- Field Marshal StorageBattery storage · 151 MW · in study
- Glory Bee StorageSolar + storage · 101 MW · in study
- Lucky Bluff BESS SLFBattery storage · 101 MW · built
- Palm Bluff Energy StorageOther · 101 MW · withdrawn
- Ambrose Energy StorageOther · 101 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem