🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Lucky Bluff BESS SLF

Lucky Bluff BESS SLF is a 101 MW battery storage request built and operating in the ERCOT interconnection queue, in Erath County, Texas.

Queue statusOperating
  1. PlanningQueued Mar 2022 (completed)
  2. ConsentedNov 2023 (completed)
  3. Construction (completed)
  4. OperatingDec 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0295
Grid region
ERCOT (Texas)
Developer
Lucky Bluff BESS LLC
Connection point (POI)
1652 Fullhouse 138kV tapped in 138kV 1641 Stephenville - 1636 Dublin
Location
Erath County, Texas
Technology
Battery: 101 MW
Total requested
101 MW
Study phase
IA
Queue status
Operational
Entered queue
29 March 2022
Agreement signed
8 November 2023
Proposed online date
November 2025
Came online
December 2025

Location

Marker shows the centre of Erath County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Erath County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem