SOLAR + STORAGE · ERCOT

Glory Bee Storage

Glory Bee Storage is a 101 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Erath County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0369
Grid region
ERCOT (Texas)
Developer
Riley Solar LLC
Connection point (POI)
Tap 345kV 1440 Comanche Switch - 1900 Comanche Peak
Location
Erath County, Texas
Technology
Battery: 101 MW · Battery
Total requested
101 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
10 June 2022
Proposed online date
April 2026

Location

Marker shows the centre of Erath County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Erath County