Ambrose Energy Storage

Ambrose Energy Storage is a 101 MW other request withdrawn in the ERCOT interconnection queue, in Erath County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedDec 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0563
Grid region
ERCOT (Texas)
Developer
Ambrose Energy Storage, LLC
Connection point (POI)
Tap 345kV 68060 Romney - 68070 Kopperl
Location
Erath County, Texas
Technology
Other: 101 MW
Total requested
101 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Entered queue
24 October 2023
Proposed online date
September 2025
Withdrawn
December 2023

Location

Marker shows the centre of Erath County; the queue data does not give exact sites.