United States › Grid › Interconnection queues › Nevada
GEOTHERMAL · WESTGeothermal project Company LM, Lyon County
Geothermal project Company LM, Lyon County is a 230 MW geothermal request with a signed interconnection agreement in the West interconnection queue, in Lyon County, Nevada, connecting to NV Energy.
Queue statusConsented
- PlanningQueued Mar 2021 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- Company LM
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- Lyon County, Nevada
- Technology
- Geothermal: 230 MW
- Total requested
- 230 MW
- Service type
- NRIS and ERIS
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 31 March 2021
- Proposed online date
- December 2029
Location
Marker shows the centre of Lyon County; the queue data does not give exact sites.
Other requests in Lyon County
- Solar + storage project Company KU, Lyon CountySolar + storage · 400 MW · agreement signed
- Solar + storage project Company LP, Lyon CountySolar + storage · 400 MW · agreement signed
- Solar + storage project Company LK, Lyon CountySolar + storage · 200 MW · agreement signed
- Solar + storage project Company LG, Lyon CountySolar + storage · 200 MW · agreement signed
- Geothermal project Company QK, Lyon CountyGeothermal · 38.5 MW · agreement signed
- Geothermal project Company KO, Lyon CountyGeothermal · 4.8 MW · agreement signed
- Other project Company MN, Lyon CountyOther · 1.3 MW · agreement signed
- Solar + storage project 25-00432, Lyon CountySolar + storage · 900 MW · in study
- Solar + storage project 25-00401, Lyon CountySolar + storage · 500 MW · in study
- Solar + storage project 25N-SG6, Lyon CountySolar + storage · 20.0 MW · in study
- Solar + storage project Company ME, Lyon CountySolar + storage · 500 MW · suspended
- Battery storage project Company OW, Lyon CountyBattery storage · 500 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem