United States › Grid › Interconnection queues › Nevada

GEOTHERMAL · WEST

Geothermal project Company KO, Lyon County

Geothermal project Company KO, Lyon County is a 4.8 MW geothermal request with a signed interconnection agreement in the West interconnection queue, in Lyon County, Nevada, connecting to NV Energy.

Queue statusConsented
  1. PlanningQueued Sep 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Company KO
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Lyon County, Nevada
Technology
Geothermal: 4.8 MW
Total requested
4.8 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
17 September 2020
Proposed online date
October 2027

Location

Marker shows the centre of Lyon County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Lyon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem