United States › Grid › Interconnection queues › Michigan
SOLAR · MISOSolar project J2001, Newaygo County
Solar project J2001, Newaygo County is a 220 MW solar request in interconnection study in the MISO interconnection queue, in Newaygo County, Michigan, connecting to METC.
Queue statusIn planning
- PlanningQueued Aug 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2001
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- KENOWA - LUDINGTON 345.0kV
- Location
- Newaygo County, Michigan
- Technology
- Solar: 220 MW
- Total requested
- 220 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 16 August 2021
- Proposed online date
- May 2025
Location
Marker shows the centre of Newaygo County; the queue data does not give exact sites.
Other requests in Newaygo County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem