United States › Grid › Interconnection queues › Arkansas
SOLAR · SPPSolar project GEN-2021-036, Little River County
Solar project GEN-2021-036, Little River County is a 204 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Little River County, Arkansas, connecting to AEP.
Queue statusConsented
- PlanningQueued May 2021 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2021-036
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Craig to Patterson 138 kV Transmission Line
- Location
- Little River County, Arkansas
- Technology
- Solar: 204 MW
- Total requested
- 204 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 14 May 2021
- Proposed online date
- November 2027
Location
Marker shows the centre of Little River County; the queue data does not give exact sites.
Other requests in Little River County
- Battery storage project GEN-2022-045, Little River CountyBattery storage · 200 MW · withdrawn
- Solar project GEN-2022-047, Little River CountySolar · 200 MW · withdrawn
- Solar + storage project GEN-2024-115, Little River CountySolar + storage · 199 MW · withdrawn
- Solar project GEN-2018-023, Little River CountySolar · 126 MW · withdrawn
- Battery storage project GEN-2022-089, Little River CountyBattery storage · 75.0 MW · withdrawn
- Solar project GEN-2022-088, Little River CountySolar · 75.0 MW · withdrawn
- Solar project GEN-2017-003, Little River CountySolar · 21.6 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem