πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· SPP

Solar project GEN-2022-088, Little River County

Solar project GEN-2022-088, Little River County is a 75.0 MW solar request withdrawn in the SPP interconnection queue, in Little River County, Arkansas, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-088
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
South Foreman 138 kV Substation
Location
Little River County, Arkansas
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
15 November 2022
Proposed online date
September 2026
Withdrawn
March 2025

Location

Marker shows the centre of Little River County; the queue data does not give exact sites.