United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
BATTERY STORAGE Β· SPPBattery storage project GEN-2022-045, Little River County
Battery storage project GEN-2022-045, Little River County is a 200 MW battery storage request withdrawn in the SPP interconnection queue, in Little River County, Arkansas, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2022 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-045
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- South Foreman - Patterson 138 kV line
- Location
- Little River County, Arkansas
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 June 2022
- Proposed online date
- December 2028
- Withdrawn
- November 2023
Location
Marker shows the centre of Little River County; the queue data does not give exact sites.
Other requests in Little River County
- Solar project GEN-2021-036, Little River CountySolar Β· 204 MW Β· agreement signed
- Solar project GEN-2022-047, Little River CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project GEN-2024-115, Little River CountySolar + storage Β· 199 MW Β· withdrawn
- Solar project GEN-2018-023, Little River CountySolar Β· 126 MW Β· withdrawn
- Battery storage project GEN-2022-089, Little River CountyBattery storage Β· 75.0 MW Β· withdrawn
- Solar project GEN-2022-088, Little River CountySolar Β· 75.0 MW Β· withdrawn
- Solar project GEN-2017-003, Little River CountySolar Β· 21.6 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem