Umbra (Stockyard) Solar

Umbra (Stockyard) Solar is a 208 MW solar request suspended in the ERCOT interconnection queue, in Franklin County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Jan 2021 (current stage)
  2. ConsentedOct 2022 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0155
Grid region
ERCOT (Texas)
Location
Franklin County, Texas
Technology
Solar: 208 MW
Total requested
208 MW
Queue status
Suspended
Entered queue
24 January 2021
Agreement signed
11 October 2022
Proposed online date
April 2026

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.