United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTLazy Frog Solar SLF
Lazy Frog Solar SLF is a 100 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Franklin County, Texas.
Queue statusIn planning
- PlanningQueued Sep 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0504
- Grid region
- ERCOT (Texas)
- Developer
- Lazy Frog Solar, LLC
- Connection point (POI)
- 11688 Thorn Tree Switch 345kV
- Location
- Franklin County, Texas
- Technology
- Solar: 100 MW · Battery
- Total requested
- 100 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 22 September 2023
- Proposed online date
- April 2028
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- Lupinus Solar 2Solar + storage · 242 MW · agreement signed
- Lupinus Solar 1Solar + storage · 162 MW · agreement signed
- Lupinus Storage 2Solar + storage · 125 MW · agreement signed
- Lupinus Solar 3Solar + storage · 101 MW · agreement signed
- Lupinus Storage 3Solar + storage · 50.9 MW · agreement signed
- Prairie Ridge (Gas - CC)Gas · 1,660 MW · in study
- Solar project GEN-2023-241, Franklin CountySolar · 93.0 MW · in study
- Lupinus Storage 1Solar + storage · 84.0 MW · in study
- Umbra (Stockyard) SolarSolar · 208 MW · suspended
- Umbra (Stockyard) BESSBattery storage · 73.0 MW · suspended
- Umbra Solar IISolar · 345 MW · withdrawn
- Umbra BESS IIBattery storage · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem