United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Lupinus Solar 3

Lupinus Solar 3 is a 101 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Franklin County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2023 (completed)
  2. ConsentedMar 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0484
Grid region
ERCOT (Texas)
Developer
Lupinus Solar 2, LLC
Connection point (POI)
1794 Monticello Tap 138 kV
Location
Franklin County, Texas
Technology
Solar: 101 MW · Battery
Total requested
101 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
23 September 2023
Agreement signed
4 March 2025
Proposed online date
September 2026

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem