SOLAR + STORAGE · ERCOT

Lupinus Storage 1

Lupinus Storage 1 is a 84.0 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Franklin County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0153
Grid region
ERCOT (Texas)
Developer
Lupinus Solar, LLC
Connection point (POI)
Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES
Location
Franklin County, Texas
Technology
Battery: 84.0 MW · Battery
Total requested
84.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
13 December 2021
Proposed online date
September 2027

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem