United States › Grid › Interconnection queues › Colorado

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Colorado — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown20943.2 GW
Active in queue43.2 GW209 requests
Agreement signed11.0 GW60 requests
Withdrawn36875.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

209 requests · page 4 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GI-CS-2025-28, Prowers County
Solar + storage
110 MWIn study Prowers, COWest Oct 2025target 2030
Battery storage project GI-TC-2024-19, Montrose County
Battery storage
100 MWAgreement signed Montrose, COWest May 2024target 2027
Battery storage project CSUT-2025-6, El Paso County
Battery storage
100 MWIn study El Paso, COWest Mar 2025target 2027
Solar + storage project GI-2024-07, Pueblo County
Solar + storage
100 MWIn study Pueblo, COWest May 2024target 2028
Battery storage project GI-TC-2024-18, Montezuma County
Battery storage
100 MWIn study Montezuma, COWest May 2024target 2027
Solar project GI-2024-17, Alamosa County
Solar
100 MWIn study Alamosa, COWest May 2024target 2030
Solar project 20-02261, Larimer County
Solar
100 MWIn study Larimer, COWest Feb 2020target 2023
Battery storage project 3RSC-2023-02, Pueblo County
Battery storage
100 MWIn study Pueblo, COWest May 2023target 2025
Solar project BHCT G52, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jun 2024target 2026
Solar project GI-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Apr 2024target 2028
Battery storage project CSUT-2025-8, El Paso County
Battery storage
100 MWIn study El Paso, COWest Mar 2025target 2028
Coal project GI-2010-8, Pueblo County
Coal
100 MWAgreement signed Pueblo, COWest May 2010target 2010
Solar project CSUT-2025-2, El Paso County
Solar
100 MWIn study El Paso, COWest Mar 2025target 2028
Solar project 5RSC-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jan 2024target 2028
Solar + storage project GI-CS-2025-10, Otero County
Solar + storage
100 MWIn study Otero, COWest Sep 2025target 2029
Solar + storage project BHCT G32, Pueblo County
Solar + storage
100 MWIn study Pueblo, COWest Apr 2022target 2025
Solar + storage project GI-DISIS-2022-22, Kit Carson County
Solar + storage
90.0 MWAgreement signed Kit Carson, COWest May 2022target 2028
Solar project BHCT G21, Pueblo County
Solar
80.0 MWIn study Pueblo, COWest Jan 2017target 2018
Battery storage project GI-SISS-2025-04, Kit Carson County
Battery storage
79.0 MWIn study Kit Carson, COWest Jul 2025target 2027
Onshore wind project GI-2025-05, Logan County
Onshore wind
75.0 MWIn study Logan, COWest May 2025target 2029
Battery storage project 1RSC-2020-02, Pueblo County
Battery storage
75.0 MWAgreement signed Pueblo, COWest Jan 2020target 2022
Onshore wind project GI-2006-1h, Prowers County
Onshore wind
75.0 MWAgreement signed Prowers, COWest Jan 2006target 2006
Solar project BHCT G28, Pueblo County
Solar
75.0 MWIn study Pueblo, COWest Feb 2020target 2023
Onshore wind project GI-2014-4, Logan County
Onshore wind
60.0 MWAgreement signed Logan, COWest Apr 2014target 2013
Solar project BHCT G19, Pueblo County
Solar
60.0 MWIn study Pueblo, COWest Apr 2015target 2019
Onshore wind project GI-2012-3, Logan County
Onshore wind
60.0 MWIn study Logan, COWest May 2012target 2013
Solar project GI-2017-5, Park County
Solar
54.3 MWAgreement signed Park, COWest Jan 2017target 2019
Solar project GI-2014-13, Alamosa County
Solar
53.0 MWAgreement signed Alamosa, COWest Nov 2014target 2016
Gas project GI-2022-1, Weld County
Gas
52.0 MWAgreement signed Weld, COWest Mar 2022target 2023
Solar project GI-2010-11, Alamosa County
Solar
52.0 MWAgreement signed Alamosa, COWest Jul 2010target 2016
Solar project GI-2014-14, Alamosa County
Solar
50.1 MWAgreement signed Alamosa, COWest Dec 2014target 2016
Battery storage project 22-07253, Weld County
Battery storage
50.0 MWIn study Weld, COWest Jul 2022target 2026
Solar project 25-041825, Larimer County
Solar
50.0 MWIn study Larimer, COWest Apr 2025target 2028
Battery storage project BHCT G50, Pueblo County
Battery storage · Black Hills Colorado Electric, LLC
50.0 MWIn study Pueblo, COWest Jun 2024target 2026
Onshore wind project GI-2007-5, Weld County
Onshore wind
50.0 MWAgreement signed Weld, COWest Mar 2007target 2008
Battery storage project 23-05032, Larimer County
Battery storage
50.0 MWIn study Larimer, COWest May 2023target 2026
Battery storage project 23-05031, Boulder County
Battery storage
50.0 MWIn study Boulder, COWest May 2023target 2026
Battery storage project GI-RSC-2025-03, Montrose County
Battery storage
50.0 MWIn study Montrose, COWest Jul 2025target 2027
Battery storage project 23-08081, Larimer County
Battery storage
50.0 MWIn study Larimer, COWest Aug 2023target 2026
Solar project GI-2014-5, Arapahoe County
Solar
50.0 MWAgreement signed Arapahoe, COWest May 2014target 2016
Onshore wind project GI-DISIS-2022-41, Kit Carson County
Onshore wind
49.6 MWPaused / redesign Kit Carson, COWest May 2022target 2028
Gas project GI-2021-2, Weld County
Gas
49.0 MWAgreement signed Weld, COWest Mar 2021target 2022
Hydro project GI-2014-7, Clear Creek County
Hydro
42.0 MWAgreement signed Clear Creek, COWest Jul 2014target 2019
Solar + storage project GI-2021-4, Conejos County
Solar + storage
42.0 MWPaused / redesign Conejos, COWest Mar 2021target 2024
Solar project GI-2017-52, El Paso County
Solar
36.0 MWAgreement signed El Paso, COWest Dec 20172019
Gas project GI-2021-3, Weld County
Gas
35.0 MWAgreement signed Weld, COWest Mar 2021target 2021
Solar project GI-2010-4, Alamosa County
Solar
30.0 MWAgreement signed Alamosa, COWest Feb 2010target 2012
Gas project GI-2020-05, Weld County
Gas
24.0 MWAgreement signed Weld, COWest Mar 2020target 2020
Solar project GI-2019-5, Garfield County
Solar
19.9 MWIn study Garfield, COWest Apr 2019target 2020
Onshore wind project GI-2013-4, Jefferson County
Onshore wind
19.9 MWAgreement signed Jefferson, COWest Jun 2013target 2015

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)