United States › Grid › Interconnection queues › Colorado
BATTERY STORAGE · WESTBattery storage project GI-TC-2024-19, Montrose County
Battery storage project GI-TC-2024-19, Montrose County is a 100 MW battery storage request with a signed interconnection agreement in the West interconnection queue, in Montrose County, Colorado, connecting to Tri-State Generation and Transmission Association.
Queue statusConsented
- PlanningQueued May 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget May 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-TC-2024-19
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Montrose 115kV Substation
- Location
- Montrose County, Colorado
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed LGIA
- Queue status
- Active
- Entered queue
- 7 May 2024
- Proposed online date
- May 2027
Location
Marker shows the centre of Montrose County; the queue data does not give exact sites.
Other requests in Montrose County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem