United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project GI-2017-52, El Paso County

Solar project GI-2017-52, El Paso County is a 36.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in El Paso County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusConsented
  1. PlanningQueued Dec 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingNov 2019 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-2017-52
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Fuller 230 kV Substation
Location
El Paso County, Colorado
Technology
Solar: 36.0 MW
Total requested
36.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility/System Impact Study Complete Facility Study Complete LGIA Signed
Queue status
Active
Entered queue
15 December 2017
Proposed online date
December 2019
Came online
November 2019

Location

Marker shows the centre of El Paso County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in El Paso County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem