United States › Grid › Interconnection queues › Colorado

SOLAR + STORAGE · WEST

Solar + storage project CSU-2020-3, El Paso County

Solar + storage project CSU-2020-3, El Paso County is a 200 MW solar + storage request in interconnection study in the West interconnection queue, in El Paso County, Colorado, connecting to Colorado Springs Utilities.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
CSU-2020-3
Grid region
West (non-ISO utilities)
Utility / transmission owner
Colorado Springs Utilities
Connection point (POI)
Williams Creek Substation
Location
El Paso County, Colorado
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
Facility Study
Queue status
Active
Entered queue
20 June 2020
Proposed online date
September 2025

Location

Marker shows the centre of El Paso County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in El Paso County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem