SOLAR · WEST

Solar project GI-2014-5, Arapahoe County

Solar project GI-2014-5, Arapahoe County is a 50.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Arapahoe County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusConsented
  1. PlanningQueued May 2014 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2016 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-2014-5
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Missile Site Substation
Location
Arapahoe County, Colorado
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
Feasibility/System Impact Study Completed Facility Study Complete LGIA Signed
Queue status
Active
Entered queue
16 May 2014
Proposed online date
December 2016

Location

Marker shows the centre of Arapahoe County; the queue data does not give exact sites.