πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

SOLAR Β· WEST

Solar project GI-2022-5, Arapahoe County

Solar project GI-2022-5, Arapahoe County is a 300 MW solar request withdrawn in the West interconnection queue, in Arapahoe County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2022-5
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Missle Site 345 kV Substation
Location
Arapahoe County, Colorado
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
Detailed status: Withdrawn 07/03/2023
Queue status
Withdrawn
Entered queue
22 March 2022
Proposed online date
December 2025
Withdrawn
July 2023

Location

Marker shows the centre of Arapahoe County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Arapahoe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem