United States › Grid › Interconnection queues › Colorado
SOLAR · WESTSolar project GI-2019-5, Garfield County
Solar project GI-2019-5, Garfield County is a 19.9 MW solar request in interconnection study in the West interconnection queue, in Garfield County, Colorado, connecting to Public Service Company Of Colorado.
- PlanningQueued Apr 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2020 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-2019-5
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Parachute Substation 24.9 kV Bus
- Location
- Garfield County, Colorado
- Technology
- Solar: 19.9 MW
- Total requested
- 19.9 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study Complete Interconnection subject to State Jurisdictional
- Queue status
- Active
- Entered queue
- 16 April 2019
- Proposed online date
- December 2020
Location
Marker shows the centre of Garfield County; the queue data does not give exact sites.
Other requests in Garfield County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem