Battery storage project 3RSC-2023-02, Pueblo County

Battery storage project 3RSC-2023-02, Pueblo County is a 100 MW battery storage request in interconnection study in the West interconnection queue, in Pueblo County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusIn planning
  1. PlanningQueued May 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
3RSC-2023-02
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Mirasol 230 kV Switching Station
Location
Pueblo County, Colorado
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Phase 1 Report Completed 12/13/2024 Phase 2 Report Completed 05/22/2025 Phase 4 Report Completed 12/0
Queue status
Active
Entered queue
19 May 2023
Proposed online date
December 2025

Location

Marker shows the centre of Pueblo County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Pueblo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem