United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project GI-2017-5, Park County

Solar project GI-2017-5, Park County is a 54.3 MW solar request with a signed interconnection agreement in the West interconnection queue, in Park County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusConsented
  1. PlanningQueued Jan 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2019 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-2017-5
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Hartsel Substation
Location
Park County, Colorado
Technology
Solar: 54.3 MW
Total requested
54.3 MW
Service type
NRIS and ERIS
Study phase
Feasibility/System Impact Study Complete Facility Study Complete LGIA Signed
Queue status
Active
Entered queue
26 January 2017
Proposed online date
March 2019

Location

Marker shows the centre of Park County; the queue data does not give exact sites.