πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

SOLAR Β· WEST

Solar project GI-2008-23, Park County

Solar project GI-2008-23, Park County is a 34.0 MW solar request withdrawn in the West interconnection queue, in Park County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2008 (completed)
  2. Withdrawn / abandonedNov 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2008-23
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Hartsel Substation
Location
Park County, Colorado
Technology
Solar: 34.0 MW
Total requested
34.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study complete System Impact Study complete Request Withdrawn 11/16/10
Queue status
Withdrawn
Entered queue
20 October 2008
Proposed online date
June 2010
Withdrawn
November 2010

Location

Marker shows the centre of Park County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Park County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem