Solar project J2987, Greene County Solar |
200 MW | In study |
Greene, IN | MISO |
Sep 2022 | target 2025 |
Solar project J1378, Fountain County Solar |
200 MW | Agreement signed |
Fountain, IN | MISO |
Apr 2019 | target 2024 |
Battery storage project J2572, Hamilton County Battery storage |
200 MW | In study |
Hamilton, IN | MISO |
Sep 2022 | target 2025 |
Onshore wind project J2509, Tippecanoe County Onshore wind |
200 MW | In study |
Tippecanoe, IN | MISO |
Sep 2022 | target 2025 |
Solar project J2848, Hamilton County Solar |
200 MW | In study |
Hamilton, IN | MISO |
Nov 2025 | target 2025 |
Prairie Creek Wind Onshore wind · Prairie Creek Wind, LLC |
200 MW | Agreement signed |
Blackford, IN | PJM |
Mar 2020 | target 2029 |
Solar + storage project J3979, Sullivan County Solar + storage |
200 MW | In study |
Sullivan, IN | MISO |
Apr 2025 | target 2029 |
Solar project J1684, Starke County Solar |
200 MW | In study |
Starke, IN | MISO |
Aug 2023 | target 2029 |
Solar + storage project J3879, Jackson County Solar + storage |
200 MW | In study |
Jackson, IN | MISO |
May 2024 | target 2030 |
Surplus; J992 Battery storage |
200 MW | In study |
Cass, IN | MISO |
Jun 2025 | target 2026 |
Battery storage project J3691, White County Battery storage |
200 MW | In study |
White, IN | MISO |
Apr 2024 | target 2028 |
Teays River Wind Farm Onshore wind · Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC |
200 MW | In study |
Blackford, IN | PJM |
Mar 2020 | target 2023 |
Solar project J4039, Montgomery County Solar |
200 MW | In study |
Montgomery, IN | MISO |
Jun 2025 | target 2030 |
Solar project J1786, Sullivan County Solar |
200 MW | In study |
Sullivan, IN | MISO |
Jun 2020 | target 2026 |
Lake Trout Solar Solar + storage |
200 MW | Agreement signed |
Blackford, IN | PJM |
Sep 2019 | target 2028 |
Battery storage project AH2-347, St. Joseph County Battery storage |
200 MW | In study |
St. Joseph, IN | PJM |
Mar 2022 | target 2025 |
Solar project J1381, Howard County Solar |
200 MW | Agreement signed |
Howard, IN | MISO |
Apr 2019 | target 2026 |
Battery storage project J3873, Gibson County Battery storage |
200 MW | In study |
Gibson, IN | MISO |
Dec 2024 | target 2029 |
Solar project J1348, Vermillion County Solar |
200 MW | Agreement signed |
Vermillion, IN | MISO |
Apr 2019 | target 2025 |
Battery storage project J3249, Vanderburgh County Battery storage |
200 MW | In study |
Vanderburgh, IN | MISO |
Apr 2024 | target 2028 |
Solar + storage project J1340, Jasper County Solar + storage |
200 MW | Agreement signed |
Jasper, IN | MISO |
Apr 2019 | target 2025 |
Solar + storage project J1336, Jasper County Solar + storage |
200 MW | Agreement signed |
Jasper, IN | MISO |
Apr 2019 | target 2025 |
Solar + storage project J1339, Jasper County Solar + storage |
200 MW | Agreement signed |
Jasper, IN | MISO |
Apr 2019 | target 2025 |
Solar project J805, Shelby County Solar |
199 MW | Under construction |
Shelby, IN | MISO |
Jun 2017 | target 2022 |
Battery storage project J2280 Battery storage |
198 MW | In study |
IN | MISO |
Mar 2022 | target 2023 |
Solar project J1063, Clinton County Solar |
195 MW | Under construction |
Clinton, IN | MISO |
Mar 2018 | 2024 |
Solar project J2353, White County Solar |
190 MW | In study |
White, IN | MISO |
Sep 2022 | target 2026 |
Solar project J4023, Clay County Solar |
185 MW | In study |
Clay, IN | MISO |
Feb 2025 | target 2029 |
Solar project J1518, Vermillion County Solar |
185 MW | In study |
Vermillion, IN | MISO |
Aug 2024 | target 2026 |
Solar + storage project AH2-153, Vermillion County Solar + storage |
180 MW | In study |
Vermillion, IN | PJM |
Feb 2022 | target 2024 |
Hoosier Line Solar Solar |
180 MW | Agreement signed |
White, IN | PJM |
Sep 2019 | target 2027 |
Sculpin Solar Solar |
180 MW | Agreement signed |
Dekalb, IN | PJM |
Aug 2019 | target 2028 |
Onshore wind project J2654, Clinton County Onshore wind |
180 MW | In study |
Clinton, IN | MISO |
Sep 2022 | target 2026 |
Solar project J2847, Starke County Solar |
180 MW | In study |
Starke, IN | MISO |
Sep 2022 | target 2026 |
Solar project J1721, Vigo County Solar |
175 MW | In study |
Vigo, IN | MISO |
Jun 2020 | target 2026 |
Solar project J643, Jasper County Solar |
175 MW | Agreement signed |
Jasper, IN | MISO |
May 2016 | 2023 |
Onshore wind project AI1-003, Huntington County Onshore wind |
170 MW | In study |
Huntington, IN | PJM |
Apr 2022 | target 2026 |
Golden Aster Solar Energy Center Solar |
160 MW | Paused / redesign |
Grant, IN | PJM |
Sep 2018 | target 2026 |
Battery storage project J1355, Laporte County Battery storage |
160 MW | Agreement signed |
Laporte, IN | MISO |
Apr 2019 | target 2026 |
Solar project J3731, Knox County Solar |
160 MW | In study |
Knox, IN | MISO |
Apr 2024 | target 2027 |
Solar project J2747, Greene County Solar |
160 MW | In study |
Greene, IN | MISO |
Sep 2022 | target 2026 |
Skycrest Solar Energy Center Solar |
155 MW | Agreement signed |
Jay, IN | PJM |
Feb 2019 | target 2026 |
Blackford Solar Energy Project Solar |
150 MW | Agreement signed |
Jay, IN | PJM |
Sep 2019 | target 2026 |
Solar project AG2-230, St. Joseph County Solar · Dumont Solar, LLC |
150 MW | In study |
St. Joseph, IN | PJM |
Mar 2025 | target 2024 |
Solar + storage project J3745, Dearborn County Solar + storage |
150 MW | In study |
Dearborn, IN | MISO |
Apr 2024 | target 2028 |
Solar project J1783, Montgomery County Solar |
150 MW | In study |
Montgomery, IN | MISO |
Jun 2020 | target 2025 |
Solar project J1027, Pike County Solar |
150 MW | Agreement signed |
Pike, IN | MISO |
Mar 2018 | target 2022 |
Solar + storage project J3733, Gibson County Solar + storage |
150 MW | In study |
Gibson, IN | MISO |
May 2024 | target 2028 |
Solar project J1482, White County Solar |
150 MW | Agreement signed |
White, IN | MISO |
Apr 2019 | 2024 |
Solar project J3145, Putnam County Solar |
150 MW | In study |
Putnam, IN | MISO |
Sep 2022 | target 2027 |