United States › Grid › Interconnection queues › Indiana

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Indiana — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown30059.6 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

300 requests · page 3 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2987, Greene County
Solar
200 MWIn study Greene, INMISO Sep 2022target 2025
Solar project J1378, Fountain County
Solar
200 MWAgreement signed Fountain, INMISO Apr 2019target 2024
Battery storage project J2572, Hamilton County
Battery storage
200 MWIn study Hamilton, INMISO Sep 2022target 2025
Onshore wind project J2509, Tippecanoe County
Onshore wind
200 MWIn study Tippecanoe, INMISO Sep 2022target 2025
Solar project J2848, Hamilton County
Solar
200 MWIn study Hamilton, INMISO Nov 2025target 2025
Prairie Creek Wind
Onshore wind · Prairie Creek Wind, LLC
200 MWAgreement signed Blackford, INPJM Mar 2020target 2029
Solar + storage project J3979, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Solar project J1684, Starke County
Solar
200 MWIn study Starke, INMISO Aug 2023target 2029
Solar + storage project J3879, Jackson County
Solar + storage
200 MWIn study Jackson, INMISO May 2024target 2030
Surplus; J992
Battery storage
200 MWIn study Cass, INMISO Jun 2025target 2026
Battery storage project J3691, White County
Battery storage
200 MWIn study White, INMISO Apr 2024target 2028
Teays River Wind Farm
Onshore wind · Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC
200 MWIn study Blackford, INPJM Mar 2020target 2023
Solar project J4039, Montgomery County
Solar
200 MWIn study Montgomery, INMISO Jun 2025target 2030
Solar project J1786, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Jun 2020target 2026
Lake Trout Solar
Solar + storage
200 MWAgreement signed Blackford, INPJM Sep 2019target 2028
Battery storage project AH2-347, St. Joseph County
Battery storage
200 MWIn study St. Joseph, INPJM Mar 2022target 2025
Solar project J1381, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2026
Battery storage project J3873, Gibson County
Battery storage
200 MWIn study Gibson, INMISO Dec 2024target 2029
Solar project J1348, Vermillion County
Solar
200 MWAgreement signed Vermillion, INMISO Apr 2019target 2025
Battery storage project J3249, Vanderburgh County
Battery storage
200 MWIn study Vanderburgh, INMISO Apr 2024target 2028
Solar + storage project J1340, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1336, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1339, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar project J805, Shelby County
Solar
199 MWUnder construction Shelby, INMISO Jun 2017target 2022
Battery storage project J2280
Battery storage
198 MWIn study INMISO Mar 2022target 2023
Solar project J1063, Clinton County
Solar
195 MWUnder construction Clinton, INMISO Mar 20182024
Solar project J2353, White County
Solar
190 MWIn study White, INMISO Sep 2022target 2026
Solar project J4023, Clay County
Solar
185 MWIn study Clay, INMISO Feb 2025target 2029
Solar project J1518, Vermillion County
Solar
185 MWIn study Vermillion, INMISO Aug 2024target 2026
Solar + storage project AH2-153, Vermillion County
Solar + storage
180 MWIn study Vermillion, INPJM Feb 2022target 2024
Hoosier Line Solar
Solar
180 MWAgreement signed White, INPJM Sep 2019target 2027
Sculpin Solar
Solar
180 MWAgreement signed Dekalb, INPJM Aug 2019target 2028
Onshore wind project J2654, Clinton County
Onshore wind
180 MWIn study Clinton, INMISO Sep 2022target 2026
Solar project J2847, Starke County
Solar
180 MWIn study Starke, INMISO Sep 2022target 2026
Solar project J1721, Vigo County
Solar
175 MWIn study Vigo, INMISO Jun 2020target 2026
Solar project J643, Jasper County
Solar
175 MWAgreement signed Jasper, INMISO May 20162023
Onshore wind project AI1-003, Huntington County
Onshore wind
170 MWIn study Huntington, INPJM Apr 2022target 2026
Golden Aster Solar Energy Center
Solar
160 MWPaused / redesign Grant, INPJM Sep 2018target 2026
Battery storage project J1355, Laporte County
Battery storage
160 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Solar project J3731, Knox County
Solar
160 MWIn study Knox, INMISO Apr 2024target 2027
Solar project J2747, Greene County
Solar
160 MWIn study Greene, INMISO Sep 2022target 2026
Skycrest Solar Energy Center
Solar
155 MWAgreement signed Jay, INPJM Feb 2019target 2026
Blackford Solar Energy Project
Solar
150 MWAgreement signed Jay, INPJM Sep 2019target 2026
Solar project AG2-230, St. Joseph County
Solar · Dumont Solar, LLC
150 MWIn study St. Joseph, INPJM Mar 2025target 2024
Solar + storage project J3745, Dearborn County
Solar + storage
150 MWIn study Dearborn, INMISO Apr 2024target 2028
Solar project J1783, Montgomery County
Solar
150 MWIn study Montgomery, INMISO Jun 2020target 2025
Solar project J1027, Pike County
Solar
150 MWAgreement signed Pike, INMISO Mar 2018target 2022
Solar + storage project J3733, Gibson County
Solar + storage
150 MWIn study Gibson, INMISO May 2024target 2028
Solar project J1482, White County
Solar
150 MWAgreement signed White, INMISO Apr 20192024
Solar project J3145, Putnam County
Solar
150 MWIn study Putnam, INMISO Sep 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)