United States › Grid › Interconnection queues › Indiana
ONSHORE WIND · MISOOnshore wind project J2509, Tippecanoe County
Onshore wind project J2509, Tippecanoe County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Tippecanoe County, Indiana, connecting to DUKE ENERGY INDIANA.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2509
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Westwood 345 kV
- Location
- Tippecanoe County, Indiana
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- October 2025
Location
Marker shows the centre of Tippecanoe County; the queue data does not give exact sites.
Other requests in Tippecanoe County
- Rainbow TroutSolar + storage · 120 MW · agreement signed
- Battery storage project J2450, Tippecanoe CountyBattery storage · 100 MW · in study
- Onshore wind project J028, Tippecanoe CountyOnshore wind · 200 MW · withdrawn
- Solar project J2060, Tippecanoe CountySolar · 170 MW · withdrawn
- Onshore wind project H026, Tippecanoe CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project J163, Tippecanoe CountyOnshore wind · 100 MW · withdrawn
- Battery storage project Y2-084, Tippecanoe CountyBattery storage · 64.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem