SOLAR Β· MISOSolar project J2060, Tippecanoe County
Solar project J2060, Tippecanoe County is a 170 MW solar request withdrawn in the MISO interconnection queue, in Tippecanoe County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2060
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Springboro - Lafayette 138 kV
- Location
- Tippecanoe County, Indiana
- Technology
- Solar: 170 MW
- Total requested
- 170 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 August 2021
- Proposed online date
- May 2025
- Withdrawn
- December 2025
Location
Marker shows the centre of Tippecanoe County; the queue data does not give exact sites.
Other requests in Tippecanoe County
- Rainbow TroutSolar + storage Β· 120 MW Β· agreement signed
- Onshore wind project J2509, Tippecanoe CountyOnshore wind Β· 200 MW Β· in study
- Battery storage project J2450, Tippecanoe CountyBattery storage Β· 100 MW Β· in study
- Onshore wind project J028, Tippecanoe CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project H026, Tippecanoe CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project J163, Tippecanoe CountyOnshore wind Β· 100 MW Β· withdrawn
- Battery storage project Y2-084, Tippecanoe CountyBattery storage Β· 64.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem