United States βΊ Grid βΊ Interconnection queues βΊ Indiana
ONSHORE WIND Β· MISOOnshore wind project J163, Tippecanoe County
Onshore wind project J163, Tippecanoe County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Tippecanoe County, Indiana.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2010 (completed)
- Withdrawn / abandonedAug 2012 (project stopped here)
- ConsentedAug 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J163
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Klondike 138 kV Substation
- Location
- Tippecanoe County, Indiana
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 10 September 2010
- Agreement signed
- 22 August 2012
- Proposed online date
- April 2014
- Withdrawn
- August 2012
Location
Marker shows the centre of Tippecanoe County; the queue data does not give exact sites.
Other requests in Tippecanoe County
- Rainbow TroutSolar + storage Β· 120 MW Β· agreement signed
- Onshore wind project J2509, Tippecanoe CountyOnshore wind Β· 200 MW Β· in study
- Battery storage project J2450, Tippecanoe CountyBattery storage Β· 100 MW Β· in study
- Onshore wind project J028, Tippecanoe CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar project J2060, Tippecanoe CountySolar Β· 170 MW Β· withdrawn
- Onshore wind project H026, Tippecanoe CountyOnshore wind Β· 150 MW Β· withdrawn
- Battery storage project Y2-084, Tippecanoe CountyBattery storage Β· 64.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem