BATTERY STORAGE · MISOBattery storage project J2280
Battery storage project J2280 is a 198 MW battery storage request in interconnection study in the MISO interconnection queue, connecting to DUKE ENERGY INDIANA.
Queue statusIn planning
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2280
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- GREENWOOD CLARK TOWNSHIP
- Location
- Indiana
- Technology
- Battery: 198 MW
- Total requested
- 198 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 28 March 2022
- Proposed online date
- June 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem