United States › Grid › Interconnection queues › Indiana
SOLAR · MISOSolar project J4039, Montgomery County
Solar project J4039, Montgomery County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Montgomery County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusIn planning
- PlanningQueued Jun 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4039
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Cayuga - Frankfort 230.0kV
- Location
- Montgomery County, Indiana
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 13 June 2025
- Proposed online date
- June 2030
Location
Marker shows the centre of Montgomery County; the queue data does not give exact sites.
Other requests in Montgomery County
- Solar project J1780, Montgomery CountySolar · 200 MW · in study
- Solar project J1783, Montgomery CountySolar · 150 MW · in study
- Solar project J1782, Montgomery CountySolar · 150 MW · in study
- Onshore wind project J754, Montgomery CountyOnshore wind · 304 MW · withdrawn
- Onshore wind project J2038, Montgomery CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J313, Montgomery CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project J714, Montgomery CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J004, Montgomery CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G949, Montgomery CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G906, Montgomery CountyOnshore wind · 200 MW · withdrawn
- Battery storage project J3689, Montgomery CountyBattery storage · 200 MW · withdrawn
- Onshore wind project G605, Montgomery CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem