ONSHORE WIND Β· MISO

Onshore wind project J754, Montgomery County

Onshore wind project J754, Montgomery County is a 304 MW onshore wind request withdrawn in the MISO interconnection queue, in Montgomery County, Indiana, connecting to Duke Energy Corporation.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedSep 2020 (project stopped here)
  3. ConsentedApr 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J754
Grid region
MISO (Midcontinent)
Utility / transmission owner
Duke Energy Corporation
Connection point (POI)
Cayuga - Nucor 345kV
Location
Montgomery County, Indiana
Technology
Wind: 304 MW
Total requested
304 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Withdrawn
Queue status
Withdrawn
Entered queue
14 November 2016
Agreement signed
11 April 2019
Proposed online date
April 2020
Withdrawn
September 2020

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem