🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

BATTERY STORAGE · PJM

Battery storage project AH2-347, St. Joseph County

Battery storage project AH2-347, St. Joseph County is a 200 MW battery storage request in interconnection study in the PJM interconnection queue, in St. Joseph County, Indiana, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-347
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Northern St. Joseph 138 kV
Location
St. Joseph County, Indiana
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
10 March 2022
Proposed online date
March 2025

Location

Marker shows the centre of St. Joseph County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in St. Joseph County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem