United States › Grid › Interconnection queues › Florida

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Florida — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25124.3 GW
Active in queue24.3 GW251 requests
Agreement signed860 MW7 requests
Withdrawn47276.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

251 requests · page 2 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 290, Suwannee County
Solar · Echo River Solar Project, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2020target 2025
Solar project 322, Sumter County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Sumter, FLSoutheast Dec 2022target 2026
Solar project 341, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2026
Solar project 611, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project FC100383, Liberty County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Liberty, FLSoutheast Dec 2025target 2029
Solar + storage project 425, Bradford County
Solar + storage · Third Party
74.9 MWAgreement signed Bradford, FLSoutheast Aug 2021target 2028
Solar project 269, Marion County
Solar · Solar FL 2018 LLC
74.9 MWIn study Marion, FLSoutheast Sep 2019target 2021
Solar project 320, Hernando County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2027
Solar project 305, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 609, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar + storage project JEA-Q011, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2026
Solar project 293, Alachua County
Solar · Pleasant Solar, LLC
74.9 MWPaused / redesign Alachua, FLSoutheast Aug 2021target 2024
Solar project 338, Hamilton County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hamilton, FLSoutheast Nov 2023target 2025
Solar project FC100006, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Madison, FLSoutheast Nov 2024target 2028
Solar project 308, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project FC100385, Suwannee County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2025target 2030
Solar project 325, Osceola County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Osceola, FLSoutheast May 2023target 2026
Solar project 503, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 507, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 534, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 497, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2029
Solar project 551, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 511, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Jan 2023target 2031
Storey Bend South
Solar
74.5 MWIn study Osceola, FLSoutheast Feb 2024target 2026
Solar project 542, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 171, Gilchrist County
Solar · Florida Renewable Partners, LLC
74.5 MWIn study Gilchrist, FLSoutheast Dec 2016target 2021
Solar project 504, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 517, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 519, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2031
Solar project 473, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Solar project 518, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 454, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2030
Solar project 541, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 546, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 547, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 493, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Jan 2023target 2028
Solar project 408, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2026
Solar project 453, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2031
Solar project 437, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2026
Solar project 596, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2023target 2031
Solar project 501, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 276, Union County
Solar · FPL
74.5 MWIn study Union, FLSoutheast Jun 2017target 2029
Solar project 526, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2029
Solar project 545, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 411, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2028
Solar project 438, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Mar 2022target 2028
Solar project 413, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2020target 2027
Solar project 283, Gilchrist County
Solar · Florida Renewable Partners, LLC
74.5 MWPaused / redesign Gilchrist, FLSoutheast Apr 2020target 2022
Solar project 475, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Solar project 515, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20152025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)