United States › Grid › Interconnection queues › Florida

SOLAR + STORAGE · SOUTHEAST

Solar + storage project 425, Bradford County

Solar + storage project 425, Bradford County is a 74.9 MW solar + storage request with a signed interconnection agreement in the Southeast interconnection queue, in Bradford County, Florida, connecting to Florida Power & Light.

Queue statusConsented
  1. PlanningQueued Aug 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
425
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
Third Party
Connection point (POI)
Deerhaven (GVL)-Bradford 138kV
Location
Bradford County, Florida
Technology
Solar: 74.9 MW · Battery
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
20 August 2021
Proposed online date
August 2028

Location

Marker shows the centre of Bradford County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Bradford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem