πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

SOLAR Β· SOUTHEAST

Solar project 554, Bradford County

Solar project 554, Bradford County is a 50.0 MW solar request withdrawn in the Southeast interconnection queue, in Bradford County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
554
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Tyndall AFB
Location
Bradford County, Florida
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 February 2023
Proposed online date
December 2028

Location

Marker shows the centre of Bradford County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Bradford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem