Solar project 269, Marion County

Solar project 269, Marion County is a 74.9 MW solar request in interconnection study in the Southeast interconnection queue, in Marion County, Florida, connecting to Duke Energy Florida.

Queue statusIn planning
  1. PlanningQueued Sep 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
269
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Solar FL 2018 LLC
Connection point (POI)
Dunnellon Town Substation
Location
Marion County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Active
Entered queue
30 September 2019
Proposed online date
December 2021

Location

Marker shows the centre of Marion County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Marion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem