United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in ISO-NE (New England) — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| CC Administrative Increase Gas |
550 MW | Withdrawn / abandoned |
| Wind Onshore wind |
536 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
529 MW | Withdrawn / abandoned |
| Meriden Gas Turbines Gas |
510 MW | Withdrawn / abandoned |
| Wind Onshore wind |
500 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
500 MW | Withdrawn / abandoned |
| Wind Onshore wind |
500 MW | Withdrawn / abandoned |
| Exciter Upgrades Gas |
492 MW | Withdrawn / abandoned |
| Simple Cycle Gas |
478 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
470 MW | Withdrawn / abandoned |
| Cape Wind Turbine Generators Onshore wind |
454 MW | Withdrawn / abandoned |
| Towantic Energy Gas |
452 MW | Withdrawn / abandoned |
| Wind Onshore wind |
450 MW | Withdrawn / abandoned |
| Offshore wind Offshore wind |
440 MW | Withdrawn / abandoned |
| Combined cycle (alt to Q442/472) Gas |
431 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
415 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
410 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
408 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
402 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
400 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
400 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
388 MW | Withdrawn / abandoned |
| Offshore wind Increase (QP909) Offshore wind |
386 MW | Withdrawn / abandoned |
| Wind Onshore wind |
385 MW | Withdrawn / abandoned |
| Simple Cycle Combustion Turbine Repowering (alternative to Q647) Gas |
378 MW | Withdrawn / abandoned |
| Gas Turbine Repowering Gas |
378 MW | Withdrawn / abandoned |
| Wind Onshore wind |
376 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
366 MW | Withdrawn / abandoned |
| Pioneer Valley Energy Center Gas |
353 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
352 MW | Withdrawn / abandoned |
| Gas Turbine (alt. to QP412) Gas |
335 MW | Withdrawn / abandoned |
| Increase to Pumping load Battery storage |
333 MW | Withdrawn / abandoned |
| Brockton Combined Cycle Gas |
332 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
326 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
326 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
325 MW | Withdrawn / abandoned |
| Combined Cycle( see # 201) Gas |
320 MW | Withdrawn / abandoned |
| Solar Solar |
319 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
315 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
313 MW | Withdrawn / abandoned |
| Billerica Power Gas |
311 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
305 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
305 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
301 MW | Withdrawn / abandoned |
| Battery Storage Increase (QP1238) Battery storage |
301 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
300 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
300 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
300 MW | Withdrawn / abandoned |
| Solar Solar |
300 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)