United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in ISO-NE (New England) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown982118.1 GW
Active in queue14.6 GW72 requests
Agreement signed8,609 MW45 requests
Withdrawn982118.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

982 requests · page 2 of 20
ProjectCapacityStatusLocationRegionQueuedOnline
CC Administrative Increase
Gas
550 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2011
Wind
Onshore wind
536 MWWithdrawn / abandoned Washington, RIISO-NE Feb 2010target 2015
Battery Storage
Battery storage
529 MWWithdrawn / abandoned Bristol, MAISO-NE Jul 2023target 2028
Meriden Gas Turbines
Gas
510 MWWithdrawn / abandoned New Haven, CTISO-NE Jul 2007target 2015
Wind
Onshore wind
500 MWWithdrawn / abandoned Aroostook, MEISO-NE Jan 2022target 2025
Battery Storage
Battery storage
500 MWWithdrawn / abandoned Middlesex, MAISO-NE Aug 2020target 2025
Wind
Onshore wind
500 MWWithdrawn / abandoned Aroostook, MEISO-NE Jan 2022target 2026
Exciter Upgrades
Gas
492 MWWithdrawn / abandoned Providence, RIISO-NE Jun 2010target 2011
Simple Cycle
Gas
478 MWWithdrawn / abandoned Essex, MAISO-NE Feb 2014target 2018
Offshore Wind
Offshore wind
470 MWWithdrawn / abandoned MAISO-NE Sep 2022target 2029
Cape Wind Turbine Generators
Onshore wind
454 MWWithdrawn / abandoned MAISO-NE Jun 2001target 2018
Towantic Energy
Gas
452 MWWithdrawn / abandoned New Haven, CTISO-NE Apr 2007target 2014
Wind
Onshore wind
450 MWWithdrawn / abandoned RIISO-NE May 2008target 2013
Offshore wind
Offshore wind
440 MWWithdrawn / abandoned MAISO-NE Aug 2021target 2026
Combined cycle (alt to Q442/472)
Gas
431 MWWithdrawn / abandoned Hampden, MAISO-NE Mar 2015target 2019
Battery Storage
Battery storage
415 MWWithdrawn / abandoned Providence, RIISO-NE Jun 2024target 2027
Combined Cycle
Gas
410 MWWithdrawn / abandoned Plymouth, MAISO-NE Oct 2009target 2015
Battery Storage
Battery storage
408 MWWithdrawn / abandoned Worcester, MAISO-NE Apr 2024target 2028
Battery Storage
Battery storage
402 MWWithdrawn / abandoned Rockingham, NHISO-NE Mar 2023target 2026
Offshore Wind
Offshore wind
400 MWWithdrawn / abandoned MAISO-NE Dec 2017target 2023
Offshore Wind
Offshore wind
400 MWWithdrawn / abandoned MAISO-NE Dec 2018target 2025
Combined Cycle
Gas
388 MWWithdrawn / abandoned Hampden, MAISO-NE Feb 2014target 2019
Offshore wind Increase (QP909)
Offshore wind
386 MWWithdrawn / abandoned MAISO-NE Apr 2021target 2027
Wind
Onshore wind
385 MWWithdrawn / abandoned Washington, RIISO-NE May 2008target 2012
Simple Cycle Combustion Turbine Repowering (alternative to Q647)
Gas
378 MWWithdrawn / abandoned Middlesex, CTISO-NE Apr 2019target 2023
Gas Turbine Repowering
Gas
378 MWWithdrawn / abandoned Middlesex, CTISO-NE Apr 2017target 2021
Wind
Onshore wind
376 MWWithdrawn / abandoned Aroostook, MEISO-NE Dec 2016target 2019
Battery Storage
Battery storage
366 MWWithdrawn / abandoned Franklin, MAISO-NE Apr 2024target 2028
Pioneer Valley Energy Center
Gas
353 MWWithdrawn / abandoned Hampden, MAISO-NE Nov 2007target 2015
Offshore Wind
Offshore wind
352 MWWithdrawn / abandoned RIISO-NE Sep 2018target 2024
Gas Turbine (alt. to QP412)
Gas
335 MWWithdrawn / abandoned Fairfield, CTISO-NE Feb 2014target 2018
Increase to Pumping load
Battery storage
333 MWWithdrawn / abandoned Berkshire, MAISO-NE Nov 2021target 2021
Brockton Combined Cycle
Gas
332 MWWithdrawn / abandoned Plymouth, MAISO-NE Nov 2006target 2019
Battery Storage
Battery storage
326 MWWithdrawn / abandoned Hartford, CTISO-NE Jul 2023target 2029
Battery Storage
Battery storage
326 MWWithdrawn / abandoned New Haven, CTISO-NE Mar 2023target 2027
Battery Storage
Battery storage
325 MWWithdrawn / abandoned Windham, CTISO-NE Nov 2021target 2028
Combined Cycle( see # 201)
Gas
320 MWWithdrawn / abandoned Providence, RIISO-NE Aug 2006target 2012
Solar
Solar
319 MWWithdrawn / abandoned Aroostook, MEISO-NE May 2022target 2026
Battery Storage
Battery storage
315 MWWithdrawn / abandoned Essex, MAISO-NE Apr 2022target 2032
Battery Storage
Battery storage
313 MWWithdrawn / abandoned Washington, RIISO-NE Jun 2024target 2027
Billerica Power
Gas
311 MWWithdrawn / abandoned Middlesex, MAISO-NE Jun 2006target 2011
Battery Storage
Battery storage
305 MWWithdrawn / abandoned Providence, RIISO-NE Oct 2022target 2027
Battery Storage
Battery storage
305 MWWithdrawn / abandoned Middlesex, CTISO-NE Jun 2023target 2026
Battery Storage
Battery storage
301 MWWithdrawn / abandoned Hampden, MAISO-NE Mar 2023target 2026
Battery Storage Increase (QP1238)
Battery storage
301 MWWithdrawn / abandoned Norfolk, MAISO-NE Feb 2023target 2027
Battery Storage
Battery storage
300 MWWithdrawn / abandoned Worcester, MAISO-NE Apr 2023target 2026
Battery Storage
Battery storage
300 MWWithdrawn / abandoned New Haven, CTISO-NE Jan 2024target 2027
Battery Storage
Battery storage
300 MWWithdrawn / abandoned New London, CTISO-NE Aug 2023target 2028
Solar
Solar
300 MWWithdrawn / abandoned Aroostook, MEISO-NE Mar 2022target 2026
Battery Storage
Battery storage
300 MWWithdrawn / abandoned Hampden, MAISO-NE Nov 2022target 2025
Page 2 of 20

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)