Brockton Combined Cycle

Brockton Combined Cycle is a 332 MW gas request withdrawn in the ISO-NE interconnection queue, in Plymouth County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2006 (completed)
  2. Withdrawn / abandonedMay 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
178
Grid region
ISO-NE (New England)
Connection point (POI)
115 kV F19 and E20 lines
Location
Plymouth County, Massachusetts
Technology
Gas: 332 MW · Oil
Total requested
332 MW
Service type
Energy only (ERIS)
Study phase
Facility Study
Queue status
Withdrawn
Entered queue
2 November 2006
Proposed online date
May 2019
Withdrawn
May 2017

Location

Marker shows the centre of Plymouth County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Plymouth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem