SOLAR + STORAGE · ISO-NECranberry Highway Solar + Battery Storage
Cranberry Highway Solar + Battery Storage is a 2.2 MW solar + storage request built and operating in the ISO-NE interconnection queue, in Plymouth County, Massachusetts.
Request details
- Queue ID
- 1022
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- The primary connection of the proposed project to Eversource Energy is located on Tremont Station 713 Transformer #1 Line #86. The site is located approximately 2.29 circuit miles from Substation 713
- Location
- Plymouth County, Massachusetts
- Technology
- Solar: 2.2 MW · Battery
- Total requested
- 2.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 24 April 2020
- Agreement signed
- 17 November 2021
- Proposed online date
- February 2022
Location
Marker shows the centre of Plymouth County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Plymouth County
- SolarSolar · 6.8 MW · agreement signed
- Cranberry Point Energy StorageBattery storage · 150 MW · built
- SolarSolar · 9.5 MW · built
- SolarSolar · 4.9 MW · built
- Combined CycleGas · 898 MW · withdrawn
- Combined CycleGas · 870 MW · withdrawn
- Combined CycleGas · 410 MW · withdrawn
- Brockton Combined CycleGas · 332 MW · withdrawn
- Battery StorageBattery storage · 189 MW · withdrawn
- Battery StorageBattery storage · 189 MW · withdrawn
- Battery StorageBattery storage · 150 MW · withdrawn
- Battery StorageBattery storage · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem