BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 150 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Plymouth County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2019 (completed)
  2. Withdrawn / abandonedSep 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
832
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid East Bridgewater 115kV substation, Lat: 42.023890°, Long: -70.966356°
Location
Plymouth County, Massachusetts
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
4 January 2019
Proposed online date
December 2021
Withdrawn
September 2019

Location

Marker shows the centre of Plymouth County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Plymouth County