United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 150 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Plymouth County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
887
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource Line 113 at Wareham 115 kV substation
Location
Plymouth County, Massachusetts
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
26 April 2019
Proposed online date
May 2026
Withdrawn
November 2023

Location

Marker shows the centre of Plymouth County; the queue data does not give exact sites.