United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 300 MW battery storage request withdrawn in the ISO-NE interconnection queue, in New London County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2023 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1436
Grid region
ISO-NE (New England)
Connection point (POI)
Line tap of the Eversource 1235 115 kV Line approximately 1200’ from Uncasville 115kV SS
Location
New London County, Connecticut
Technology
Battery: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
29 August 2023
Proposed online date
June 2028
Withdrawn
October 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New London County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem