Bloom Energy Fuel Cell

Bloom Energy Fuel Cell is a 10.2 MW other request built and operating in the ISO-NE interconnection queue, in New London County, Connecticut, connecting to NU.

Queue statusOperating
  1. PlanningQueued Aug 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
912
Grid region
ISO-NE (New England)
Utility / transmission owner
NU
Connection point (POI)
Eversource Willimantic 14S
Location
New London County, Connecticut
Technology
Other: 10.2 MW
Total requested
10.2 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
23 August 2019
Proposed online date
October 2021

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New London County