🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

NUCLEAR · ISO-NE

Increase Existing Capacity

Increase Existing Capacity is a 70.0 MW nuclear request built and operating in the ISO-NE interconnection queue, in New London County, Connecticut.

Queue statusOperating
  1. PlanningQueued Nov 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
183
Grid region
ISO-NE (New England)
Connection point (POI)
CL&P Millstone 345 kV Substation
Location
New London County, Connecticut
Technology
Nuclear: 70.0 MW
Total requested
70.0 MW
Service type
Other
Study phase
IA Executed
Queue status
Operational
Entered queue
17 November 2006
Proposed online date
November 2008

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New London County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem