BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 257 MW battery storage request withdrawn in the ISO-NE interconnection queue, in New London County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2023 (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1432
Grid region
ISO-NE (New England)
Connection point (POI)
Direct tap into the 115kV Uncasville Substation
Location
New London County, Connecticut
Technology
Battery: 257 MW
Total requested
257 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
11 August 2023
Proposed online date
September 2028
Withdrawn
August 2024

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New London County